If a developer company or an individual property owner wishes to construct building in Dhaka city, permission from the concerned government authority is required to begin construction. In Dhaka city, RAJUK- Rajdhani Unnayan Kartripakkha has the development authority of the capital and approves building design and plan before the start of a project. Although the approval process is a bureaucratic and lengthy process, here is a guideline for the RAJUK Plan approval procedure.
There are several steps to follow ( at least two and minimum four steps to complete ) :
1. Land use clearance ( applicable for unplanned area )
2. Special project permit for large or specialized projects ( if applicable )
3. Building permit ( mandatory )
4. Occupancy Certificate ( mandatory )
01. Land Use Clearance ( if applicable )
At first, a Town Planning Application ( Form 101 ) has to be filled and submitted for Land Use Clearance as per RAJUK Town Planning in different areas of Dhaka Metropolitan city.
The documents required for this clearance includes:
A ) 3 copies of application form signed by the applicant
B ) 3 copies of 15 cm x 20 cm servery map ( scale 1:5,000 or 1:10,000 ) showing site map plan A in mouza map of location signed by the applicant.
C) Receipt of required Government fee deposited.
After this, a site inspection is carried out by RAJUK and a report with site related information is given to the Town Planning section.
The site related information includes:
Location of land
Land use within 250 meter radius of land
Name and width of nearest main road
Name and width of nearest road connecting plot
Existence of following within 250 m of the plot- main road, market, station, airport, historical structure, river terminal, etc
Average road benchmark elevation
Land use around north, south, east, west sides of land
Other important information
After thorough study of the report by the Town Planner, permission is given to the developer company or applicant for a 24-month period during which plan has to be submitted to RAJUK.
02. Special Project Permit ( if applicable )
If a project is considered special or big which is determined by the Town Planner, additional information apart from the above-mentioned ones has to be provided for clearance.
( application form 201 )
The additional information includes: (11 set )
Proposed development
Total land area
Maximum ground coverage
Total floor area
Total number of floors above plinth
Total number of basements
Total number of apartments for residential properties
Total floor area
Number of existing structures within the area
Approximate total electricity requirement
Approximate total water consumption
Proposed project development time in months with number of phases and duration of each phase
Covered area of each floor of each type of use in a table
Along with the above information, the following documents are also required ( 1 set )
Purchase ownership deed
Relevant deed and permission if plot has been government allotted
Receipt of payment of required fee
FAR calculation
Documents and drawings as per requirement
Land use Clearance, if required
Similar to non-special projects, the report is scrutinized by Town Planner, after which permission is granted with a validity of 24 months during which plan has to be submitted to RAJUK.
If the building to be constructed is more than 10 storied or above 33 meter in height, then for RAJUK plan approval, Departmental Clearance from following 10 authorities are required by applying in plain paper with location details and related drawings.
1) Department of power division (DPDC) for electrical load requirement
2) Water and sewage authority WASA for water consumption requirement
3) Titas gas & Transmission authority for gas requirement
4) Fire service for fire safety drawing clearance
5) Civil aviation for building height permission
6) Department of environment
7) Dhaka traffic control authority (BTCA )
8) Dhaka City Corporation (DCC)
9) DCC Ward Commissioner
10) Dhaka Metropolitan Police (DMP)
03. Building Permit ( RAJUK Plan Approval )
After receiving Land Use Clearance ( if applicable ) and all the other Departmental Clearances ( for spacial project ) , another application (form 301) of RAJUK has to be submitted to concerned officer/ committee of RAJUK for approval along with the required fee.
The application requires the following data:
Name of applicant
Present address
Type of use of proposed building
Details of proposed land with area
Details of type of use with area
Measurements of plot in all four sides with location of North, South, East, West in meters
Total floor area of proposed project
Number of apartments per floor for residential properties
Number of floors above plinth
Basement covered with percentage of land area
Floor area of different types of use
Width of adjacent roads in front, rear, left and right side
Details of existing structure if present
Set back length in meter on front, rear, left and right side.
The required documents are:
Purchase/Gift/Exchange Deed of land
Allotment Deed, if allotted by Government
Receipt of payment of required fee
FAR calculation
Documents and drawings as per requirement
Land Town Planning clearance
Special project clearance, if required
Indemnity Bond, if required
Soil test report, if required
Required plan, elevation, section
No objection certificate of other departments, if required.
After relevant data along with documents have been submitted, concerned inspector carries out site inspection and provides detailed report to the concerned authority. The concerned officer then presents the documents to the “Building Construction” committee with recommendations required for plan approval.
After satisfactory fulfillment of all the requirements, the committee members of RAJUK approves the drawing with detail number and reference and delivers the approval to the Developer Company or applicant.
04. Occupancy Certificate ( After completion of construction )
To acquire Occupancy Certificate need to apply ( Application Form 401 )along with the following documents :
1. Building Completion Report
2. As built Architectural Drawings
3. Structural Design
4. Building Services
After the application submission , Authority will visit and Inspect the site with in 15 days and Issue the certificate. This occupancy certificate is valid for 5 years. This certificate need to be renewed every 5 years.
You Can Contact us for more details :
Ar. Jewel Barua ,MIAB
Architect , Studio 16 Architects
Mobile : +8801717222907
Email : info.s16a@gmail.com
#RAJUK #RAJUKDRAWINGAPPROVAL #RAJUKDRAWING #RAJUKPLAN #RAJUKPLANAPROVAL #PLAN #DRAWING #OCCUPANCYCERTIFICATE #RAJUKOCCUPANCYCERTIFICATE #RAJUK #OCCUPANCY #CERTIFICATE #LANDUSECLEARANCE #LANDUSE #OCCUPANCY #CERTIFICATE #Rajdhani #Unnayan #Kartripakkha #RajdhaniUnnayanKartripakkha #BD #DHAKA #GOVT #BANGLADESH #CDA #ARCHITECT #ENGINEER #PLANNER #S16A #S16Achitects